Project overview:
Renewing and upgrading the Penrith WRP dewatering process to improve environmental performance, service reliability, and meet growth demand;
- Installing a prefabricated switchroom and new switchboards
- Installing new polymer system
- Installing a Waste Activated Sludge (WAS) buffer tank
- Replacing aging thickening systems
- Adding a recuperative thickening process
- Replacing centrifuge and outloading systems
Delivery Partners:
Electrical – Thompson Controls Specialist Fabrication – GSJ Fabrication
Did You Know
This was the first treatment project to mobilise for P4S (across all regions) in early 2021.
The facts:
- 220,000 customers across the network
- 1km welded stainless pipe
- 30 plant shutdowns
- 20 cutovers